The following represents a project that should be scheduled using cpm
The following represents a project that should be scheduled using CPM:
Times (DAYS)
Activity Immediate Predecessors a m b
A. – 1 3 5
B – 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C,D 3 4 5
G D,E 1 4 6
H F,G 2 4 5
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?

How it Works

1
It only takes a couple of minutes to fill in your details, select the type of paper you need (essay, term paper, etc.), give us all necessary information regarding your assignment.


2
Once we receive your request, one of our customer support representatives will contact you within 24 hours with more specific information about how much it'll cost for this particular project.


3
After receiving payment confirmation via PayPal or credit card – we begin working on your detailed outline, which is based on the requirements given by yourself upon ordering.


4
Once approved, your order is complete and will be emailed directly to the email address provided before payment was made!